Tunnels and roads that use less power: the Canary plan to cut energy use by 52%

La Cumbre tunnel on La Palma now generates 67% of the energy it uses from its own solar panels. The Canary Islands government estimates that over twenty years it will avoid more than 402 tonnes of CO₂ and save more than €40,000. It is a small installation, but it is the kind of project the government wants to repeat across the islands’ road network.

The plan was discussed on 17 and 18 November at the first Canary Roads Congress, held at the Alfredo Kraus Auditorium and Congress Centre in Las Palmas de Gran Canaria and organised by the Spanish Road Association with the regional government and more than 250 engineers from across Spain. There, the regional director general for road infrastructure, Rosana Melián, presented the energy diagnosis behind the so-called Green Strategy.

These are the numbers. The Canary roads covered by the analysis use 46.8 gigawatt-hours a year, with an electricity bill of about €7.3 million. Tunnels take 29.2 of those and open-air sections 17.6. The goal is a 52% cut, to about 22.6 gigawatt-hours, saving roughly €5 million and 15,499 tonnes of CO₂ every year. The tools: LED lighting instead of conventional lamps, systems that adjust consumption to actual use, and infrastructure spaces such as tunnel mouths and junctions used to generate renewable power.

Some of it is already running. Besides La Cumbre, the government has brought self-consumption systems into service in the El Bicho tunnel on Tenerife and the Pino Seco tunnel on Gran Canaria. The pilot projects presented at the congress also include the Butihondo junction on Fuerteventura. Pablo Rodríguez, the regional minister for public works, said the work shows that renewables can be built into road infrastructure.

One detail does not add up. In 2025 the same department spoke of consumption of about 28 gigawatt-hours a year and possible cuts of up to 80%. The figures presented now start from a higher base and set a more cautious target. The difference has not been explained publicly. It may come from a wider scope of analysis, but that remains a guess.

How much does all this matter to the islands’ power system? Not much, in absolute terms. The Canaries’ real problem lies elsewhere. In the week before 12 November, according to grid operator Red Eléctrica, renewables covered 13.1% of demand, up from 5.2% the week before, and the islands are still 44.9 points short of their 2030 target. In mid-October the regional minister for ecological transition, Mariano H. Zapata, told parliament that more than 15% of the renewable energy produced is lost for lack of storage.

Cutting the power used by tunnels and streetlights does not fix that. It does lower a public bill, and every gigawatt-hour not consumed is one the thermal power stations do not have to generate. At the congress, Guillermo Llopis, director general for roads at Spain’s Transport Ministry, pointed to the Folgoso tunnel in Galicia, where electricity use fell 61.7% between April 2024 and April 2026.


Sources: Telde Actualidad on the Canary Roads Congress (https://teldeactualidad.com/art/186112/canarias-impulsa-carreteras-sostenibles-i-congreso-canario-carreteras); Canary Islands Government, congress announcement (https://www3.gobiernodecanarias.org/noticias/canarias-celebrara-el-i-congreso-canario-de-carreteras-abordando-retos-y-oportunidades-de-las-vias-insulares/) and 2025 Green Strategy figures (https://www3.gobiernodecanarias.org/noticias/la-consejeria-avanza-en-su-estrategia-verde-para-transformar-las-carreteras/); RTVC, La Cumbre tunnel (https://rtvc.es/instalacion-fotovoltaica-la-cumbre-consumo-energetico-4-agosto-2026/); Canary Islands Government, La Cumbre, El Bicho and Pino Seco (https://www3.gobiernodecanarias.org/noticias/hemeroteca/la-instalacion-fotovoltaica-del-tunel-de-la-cumbre-evitara-la-emision-de-mas-de-402-toneladas-de-co2/); Red Eléctrica via Teneriffa News (https://www.teneriffa-news.com/es/actualidad/noticias-de-canarias/red-electrica-las-renovables-cubren-mucha-mas-electricidad-en-canarias_1491100.html); lost renewable energy (https://www.moncloa.com/2026/10/14/canarias-renovable-almacenamiento-salto-chira-3448061).