After the 2 November blackout, the Canaries fast-track at least 16 MW of batteries for La Palma

On 2 November La Palma went completely dark: 50,508 supply points lost power. The cause is still unknown.

Nine days on, the regional energy department has launched an emergency tender for at least 16 MW of batteries with two hours of storage, in 4 MW or 8 MW modules, able to react automatically and restart the grid unaided. Award is due within a month and operation in 2027. No cost has been published.

Energy minister Mariano H. Zapata calls it record time, but the islands had been asking since 2024 and Madrid only allowed batteries as an emergency measure on 30 June. He also says batteries are no substitute for overdue investment in generation and grids. The core problem, in his view, is the ageing Los Guinchos plant. Endesa pulled out of the first state tender for new generation, and the Canaries now want 64 MW against the ministry’s 52.

On Monday 9 November the cabinet released the first €68 million of a €100 million surplus for post-eruption reconstruction. The money goes to Nieves Lady Barreto’s presidency department for ash removal, EU farm aid, payments for second homes and other buildings, and support for the island and Valle de Aridane councils. €32 million remains.

The regional government says that under the 2024-2027 plan (€200m from the Canaries, €400m from Madrid) it will have paid €400m, while Madrid has sent only €100m, in 2023. The sources we checked carry no response from the ministry.