Canaries lose over 15% of renewable power: storage needed

More than 15% of the renewable power generated in the Canary Islands goes unused. At certain hours each island’s grid simply cannot absorb it, and there is nowhere to store it. Energy minister Mariano Hernández Zapata told the regional parliament as much, answering a question from Jesús Ramos of the Gomeran party ASG.

Every island runs its own small, isolated power system. When wind and sun exceed demand, output is curtailed; when they drop, fossil plants fill the gap. Zapata acknowledged that conventional generation has to stay available for emergencies, since batteries cannot yet cover long periods.

The fixes differ by island. Gran Canaria is building the Salto de Chira pumped-hydro plant, with about 200 MW of turbines and 3,500 MWh of storage. Tenerife plans a similar 200 MW plant at Güímar, costing more than €1 billion according to Atlántico Hoy. Since 1 July Tenerife and La Gomera have been linked by cable into a single system.

El Hierro remains the outlier. Its Gorona del Viento wind and pumped-storage plant met the island’s entire demand for over 1,000 hours in 2025, and renewables exceed 60% of supply there, against under 20% on the other islands.

On La Palma, a study by the Canary Islands Institute of Technology proposes a first phase of 30 MW and 600 MWh at Laguna de Barlovento. Lanzarote and Fuerteventura lack the elevation for pumped hydro. La Gomera has approved three battery projects of about 2 MW each at its wind farms.

Zapata wants Madrid to finish a decree setting how batteries are paid in non-mainland systems, an amendment to Royal Decree 738/2015.

Rooftop solar has grown from about 136 MW in 2023 to more than 302 MW in June 2026, across 24,817 installations, yet it covers only 2.5% to 3% of demand by the government’s estimate. None of the big storage plants has a confirmed start date in the sources we checked.