Thirty months. That is how long the works on the Gran Canaria stadium are expected to last, now that the island council (Cabildo) has formally awarded them, with the stated aim of handing the venue over a year before the 2030 World Cup. The winner is the joint venture of OHLA and Grupo Sando, at €192,888,434.21 before IGIC (the Canary sales tax), according to elDiario.es on 28 October.
The numbers, with sources. The Cabildo’s Instituto Insular de Deportes made the award; of that sum, €46.7 million (about 24.2%) is earmarked for labour. The project involves demolishing the structures being replaced, installing new elements and a roof. The Cabildo says the renovation meets UEFA, Spanish football federation and FIFA requirements. On 5 October the same paper had reported that with IGIC the amount rises to €206.3 million, €28.5 million below the €234.8 million tender ceiling, and that the contract could be signed at the end of November. The first tender, before the summer, drew no bids; the second attracted three groups: OHLA with Sando, Ferrovial with San José and Iniciativas Canarias, and Sacyr with Construplan and Bitumex.
Then there is FIFA’s calendar. On 27 October the organisation announced that in November and December 2026 a delegation will visit candidate cities and stadiums in the three host countries, Spain, Morocco and Portugal. For Spain the list includes Barcelona, Bilbao, Las Palmas de Gran Canaria, Madrid, San Sebastián, Seville and Zaragoza, and others may be added. The meetings will cover authorities, stadium operators, transport and accommodation. One caveat: RTVC’s headline mentions nine cities, but the body text lists fifteen across the three countries, so that number is unreliable.
To get a sense of what will be examined, the previous visit helps. In September 2024 FIFA technicians looked at Gran Canaria’s airport, training grounds, hotels in the capital and the south, the Gran Canaria Arena, fan-zone sites at Santa Catalina and the stadium project. They asked for data on air and sea links, bed capacity and the ability to run mass events with emergency plans. In other words, the match is also played outside the stadium.
What we do not know, because the sources read do not say: the final capacity, how many matches the venue could host (the number and type of games will be decided only after host cities are confirmed), what happens to the home club during the works, and how the project will be funded. Neither elDiario.es piece reports criticism or reactions, and some may well follow.
For the island, the impact of an event like this starts before kick-off. A 30-month project with nearly a quarter of its cost in labour means work for local builders, but also traffic, noise and logistics in Las Palmas. And FIFA’s November and December assessment will be the first time the island has to show, on paper and on the ground, that it has enough beds, flights and security plans for a world tournament. The next milestone is the contract signing, expected at the end of November.